Rust Bullet, LLC will be closed for the Christmas and New Year’s Day holidays from Tuesday, December 24, 2024, until January 2, 2025. Most standard, in stock orders received prior to 1:00 pm PST on Monday, December 23rd, will ship on Monday, December 23rd. Orders received after 1:00 pm PST on December 23rd will be scheduled to ship on or after January 2, 2025. You will receive an email notice with tracking information once your order has been processed for shipment. Thank you, we appreciate your business and wish everyone a very Merry Christmas and a Happy New Year!

Support@RustBullet.com

Transnet Cranes

[one_full]

Project Information:

Project Name: Transnet Cranes

Contractor and Applicator: Goldseal Rustproof Services

Application: Brush & Roller

Belville, ZA

Rust Bullet Standard

2012

Project Description:

Workman on site: 12
Application Area (In Square Meters): 3,620
New steel required: 8 tons

Engineers – Gravity Engineering

STRUCTURAL REFURBISHMENT

  • High Pressure clean of corroded Areas with Bi-Carb
  • Applied Rust Bullet to the whole of the crane
  • Replaced severely corroded steel in respect of crane access walkway stairs and runs. Replaced with 3CR12.
  • Replaced all crane access walkway stair platforms
  • Replaced Operators platform with 3CR16
  • Replaced all Bolts and Nuts that have mushroomed
  • Replaced severely corroded steel in respect of hand rails on access, stairs, walkways, platforms, grab and Girder
  • Replaces all power Boxes and electrical cables.